The scientific program of the event includes Technical Visits to relevant geotechnical sites, that will take place on Friday, the 30th of august 2024.
Participants must be equipped with suitable foot protection (boots) and inform the organisation (by email: ecsmge2024@leading.pt) for the need to supply other personal protective equipment (helmet and high visibility vests)
Considering the increasing effects ofheavy/torrential precipitation, exponentiated by growing land use, underground construction and climate change effects, the Lisbon Drainage Master Plan (LDMP, or PGDL in Portuguese) aims to better protect Lisbon from flood events.
The actions of the PGDL can generically be embodied in 4 main issues:
- Control at the starting point with the construction of retention/infiltration basins and trench drains;
- Basin transfers - construction of 2 tunnels with an internal diameter of 5.5 m and overall length of approximately 6 Km;
- Reinforcement/renovation of the sanitation network (domestic and rain water sewers);
- Improved knowledge of Lisbon’s sanitation system, as well as its operation/monitoring.
Preliminary Programme:
9:00 am – Bus admittance and departure from the Meo Arena Parking meeting point (10 min tolerance)
9:30 am – Arrival at the Association of Portuguese Engineers (Ordem dos Engenheiros - OE) headquarters premises
9:45 am – Admission at the OE auditorium
10:00 am – Opening of the Presentation session
10:15 am – Technical presentation of the Plot 2 of the Lisbon Metro extension, carried out by a representative of the “Metro de Lisboa” and by a representative of the Project Construction Companies
10:50 am – Technical presentation of the Lisbon Drainage Master Plan carried out jointly by a representative of the “Plano de Drenagem de Lisboa” and by a representative of the Project Construction Companies
11:25 am – Session closing, followed by the admittance of the participants in the correspondent bus
12:00 pm – Arrival at the construction site located at “Obra túneis de drenagem de Lisboa, Quinta do Zé Pinto, Lisboa” (near the Infinity Tower) and beginning of the technical visit
1:00 pm – Conclusion of the technical visit and bus admittance
1:30 pm – Arrival at the Meo arena parking meeting point
Photo: Leonardo Negrão/Global Imagens
In cooperation with:
The Plot 2 of the Lisbon Metro extension features extremely complex geotechnical interventions in a dense urban area, including:
- More than 22m deep anchored/propped reinforced concrete cast in situ bored pile retaining walls for the Santos station accesses and cut & cover tunnel sections;
- More than 22m deep anchored/propped reinforced concrete cast in situ diaphragm retaining walls for cut & cover tunnel sections and ventilation shafts;
- NATM tunnelling construction;
- Underpinning of existing buildings with deep foundation elements interacting with the tunnel construction;
Preliminary Programme:
9:00 am – Bus admittance and departure from the Meo Arena Parking meeting point (10 min tolerance)
9:30 am – Arrival at the Association of Portuguese Engineers (Ordem dos Engenheiros - OE) headquarters premises
9:45 am – Admission at the OE auditorium
10:00 am – Opening of the Presentation session
10:15 am – Technical presentation of the Plot 2 of the Lisbon Metro extension, carried out by a representative of the “Metro de Lisboa” and by a representative of the Project Construction Companies
10:50 am – Technical presentation of the Lisbon Drainage Master Plan carried out jointly by a representative of the “Plano de Drenagem de Lisboa” and by a representative of the Project Construction Companies
11:25 am – Session closing, followed by the admittance of the participants in the correspondent bus
12:00 pm – Arrival at the construction site located at “Rua das Francesinhas, Lisboa” and beginning of the technical visit
1:00 pm – Conclusion of the technical visit and bus admittance
1:30 pm – Arrival at the Meo arena parking meeting point
In cooperation with:
Alqueva, located at Alentejo region, is today an example of innovation and sustainability.
The hydropower powerhouse of Alqueva I is located at the Guadiana river, and started operating in 2003, with the objectives of electricity supply, public water supply, irrigation of agricultural land and implementation of leisure and tourism infrastructures. The Alqueva I powerhouse is equipped with two Francis pump-turbine units, which have a total capacity of 2 × 128 = 256 MW in turbine mode.
The powerhouse of Alqueva II is in the right bank of the river and started operation in 2012. This additional powerhouse is also equipped with two reversible units of Francis turbines, with the same power of 256 MW, and an underground hydraulic circuit with independent tunnels with a diameter of 8,5m and 350m long.
The EDP’s pioneer Floating Photovoltaic powerplant, the largest in Europe in a reservoir, inaugurated in 2022, will be another focus of this technical visit. The anchoring and cable system was designed to face the variation of 23 meter of water level. This project can produce 7,5GWh annually, supplying 1,500 homes and avoiding the emission of more than 2,600 tons of CO2.
Preliminary Programme:
8:45 am – Bus admittance and departure from the Meo Arena Parking meeting point (15 min tolerance)
11:00 am – Arrival at the site and boat visit to the floating photovoltaic powerplant located at the artificial lake (technical explanation along with the visit)
12:00 pm – Technical discussion on the platform and presentation of the hydroelectric powerhouses
1:00 pm – Light lunch at the Alqueva I powerhouse
2:00 pm – Technical visit to Alqueva I powerhouse and (depending on the ongoing maintenance works) powerhouse II
4:00 pm – Bus admittance and return to Lisbon
6:00 pm – Arrival at the Meo arena parking meeting point
In cooperation with:
The Metro do Porto lines are a reference all over the world marked by the construction works during the first years of the 21th century.
Nowadays, works are taking place with the expansion of the Yelow Line (Linha D), which will start operating within this year, the fully underground Pink Line (Linha G) and the Rubi Line, which includes a new bridge spanning the Douro River.
In August, the Pink Line (Linha G), under construction by Ferrovial and ACA in an extremely complex geological environment and in a dense urban area, will be in an advanced stage allowing a visit to this outstanding endeavour.
This new project, located in the heart of Oporto city centre, includes a 3km extension of Oporto light rail system, with 4 underground stations (Liberdade, Galiza, Hospital de Santo António and Casa da Música) and will improve access to areas with significant business, residential, and healthcare components, attracting many passengers and promoting the use of public transportation.”
Preliminary Programme:
07:45 am - Bus admittance and departure from the Meo Arena Parking meeting point (15 min tolerance)
11:00 am - Arrival at the construction site - Boavista | Casa da Música Station
11:15 am - Technical presentation of the Line G carried out by representatives of Ferrovial/ACA Construction and Metro do Porto
12:00 am - Technical visit to BCM works - Boavista | Casa da Música.
14:00 am - Light lunch at the construction site
16:00 am - Bus admittance and return to Lisbon
For this visit, if participants have any need for (mandatory) foot protection equipment (boots), please send us information about the footwear size by e-mail.
In cooperation with:
The Entrecampos Project, with the aim to requalify the urban block where previously was installed the Lisbon Amusement Park, is one of the majors ongoing in Lisbon:
Preliminary Programme:
9:00 am – Arrival at the Fidelidade headquarters, located at Av. Álvaro Pais 15-11, Lisboa;
9:15 am – Admission at the Fidelidade headquarters building;
9:30 am – Technical presentation of Entrecampos Project carried out by representatives from the project developer and from the retaining wall design office;
10:45 am – Session closing and departure to the construction site (walking distance location =>700m aprox. 10-minute walk);
11:00 pm – Arrival at the construction site entrance and beginning of the technical visit;
12:00 pm – Return to the site entrance and conclusion of the technical visit;
In cooperation with: